Thursday, Nov. 12 - Start editing those assets! Assets! Assets! Assets!
Tuesday, Nov. 17 – Have all my assets made and complete, and organized in After Effects so they are easy to find.
Thursday, Nov. 19 – Start on animation and building the comps
Tuesday, Nov. 24 – Rough draft complete and critiqued in class.
Wednesday, Nov. 25 - Start suggested fixings to the project and tightening up areas that need it most.
Thursday, Nov. 26 – Thanksgiving!
Tuesday, Dec. 1 - Have Second draft complete, and start editing and working in sounds.
Thursday, Dec. 3 – Have another critique to cover any major issues, and suggestions on the sound improvement if needed.
Tuesday, Dec. 8 – Work on Dvd and minor issues with final project before turn in.
Thursday, Dec. 10 – Final Due.